SG- S007导线点复测记录工程名称: ×××施工单位: ×××复测部位: NF219 、NF220 测量控制点日期: ×××年 ××月××日测点测角方位角距离纵坐标增量横坐标增量纵坐标横坐标备 注(°′″)°′″(m)( m)(m)( m)( m)△X△YXYNF22043140911709.33616195.096测量仪器NF22911946.68316194.415采用:2330431.493-23.007-21.5061614010苏光: OTSK111923.67616172.90956534 型1831574.751-74.633-4.2391022143全站仪K211849.04316168.67002No.05050822458141.655-100.224-100.1081019839K311748.81916068.5624724337140.477-62.396-125.85855K467291511686.42315942.7041310717.682-11.748+13.4560910530K511674.67515956.16000563708121.925+67.080+101.814K62152811741.75516057.9743292053859.110-2.162+59.073K71990511739.59316117.047431111183.706-30.257+78.04919NF20011709.33616195.09668385035950NF21911946.68316194.41508计算(另附简图) :结论: 精度可靠,满足施工要求。
1.角度闭合差:f 测 = ±14 ″f 容= ±24 ″n24"972"2.坐标增量闭合差:f x= ±0.022″f y =-0.018m3.导线相对闭合差: f = ±0.028mK=1/23964观测: ××× 复测: ××× 计算: ××× 注册建造师(技术负责人) :×××四川省建设厅制。